Kestrel expansion project, aimed to increase DUBAL’s (Dubai Aluminium) smelting capacity by about 170,000 tones. It involved retrofitting, upgrading and extending Dubal’s initial three potlines and extending its potline number four, while being designed to drastically cut Dubal’s emissions of carbon dioxide and nitrogen oxide.

Client
Dubai Aluminium Company (DUBAL)
Main Contractor
Tiger Steel Engineering LLC
Consultant
K Home International Limited
Implementaion Peroid
2004-2005
Project Location
Dubai, U.A.E
Scope of Work
Supply and erection of 8,500 t steel structure, 4 km of crane rails and all the electrical and lighting works associated with the potline structures.